SiteGrid Hybrid PowerTemporary power solution – interactive digital twin
NORMAL OPERATION
Drag to rotate · scroll to zoom · right-drag to pan · click the ATS
X500 SOC
ATS / SWITCHING SYSTEM
SELECT A SOURCE TRANSFER TO DEMONSTRATE
SITE SUPPLY (HISTORY)
Make-Before-Break ATS recommended where budget permits and uninterrupted power during source transfer is critical.
A conventional break-before-make transfer opens the old source before the new one closes. The short gap can make site drives trip or need resetting.
BATTERY REDUNDANCY
--
Battery-only support remaining
Runtimes assume the modelled peak site demand (~353 kW) less the 2 × 60A grid contribution (~83 kW), i.e. ~270 kW drawn from the battery.